Effective October 1, 2012  

 

 

Schedule "A" — residential and farm service – flat rate

Electric Grid Connection Fee: $30.34 per month
All kWh $0.10023 per kWh
Tracking clause applicable to all kwh $0.002175 per kWh
Total per kWh $0.001130 per kWh

 

Schedule "RS" — optional residential and farm service – seasonal

Electric Grid Connection Fee: $30.34 per month
All kWh per month:  
*June, July, August $0.13214 per kWh
*Dec., Jan., Feb. $0.10814per kWh
*Sept., Oct., Nov., *March, April & May $0.07770 per kWh
Tracking clause applicable to all kwh $0.001130 per kWh

* Rate changed on billing cycle date of that month.

 

Schedule "B" — commercial and small power service

Electric Grid Connection Fee:  
Single-phase service $30.97 per month
Three-phase service $43.97 per month
Tracking clause applicable to all kWh $0.001130 per kWh
All kWh per month:  
June, July, August $0.13169 per kWh
Dec., Jan., Feb. $0.10864 per kWh
Sept., Oct., Nov., March, April & May $0.07661 per kWh

 

 

Schedule "LP" — large power service

Electric Grid Connection Fee: $60 per month
Demand Charge:  
June, July, Aug. $19.53 per kW
Dec., Jan., Feb. $14.18 per kW
Sept., Oct., Nov., March, April, & May $10.67 per kW
Energy charges:  
All kWh $0.04770 per kWh
Tracking clause applicable to all kWh $0.001130 per kWh

 

 

Schedule "OSL" — monthly outdoor security light service


Security lights:

175-watt mercury vapor $7.41 per month
400-watt mercury vapor $14.14 per month
100-watt high pressure sodium $7.41 per month
250-watt high pressure sodium $12.58 per month

Flood lights:

400-watt mercury vapor $14.66 per month
1,000-watt mercury vapor $31.23 per month
250 watt high pressure sodium $12.58 per month
400-watt high pressure sodium $17.76 per month

The above charges are for security lights installed on existing REMC poles. If a new pole needs to be installed to serve the security light, the above costs will increase by $4 per month.


Collection Charges Not Requiring Pole Top Disconnect

Collection charge per trip/not requiring pole top disconnect.

$35.00
Reconnect fee disconnected for non-payment/ not requiring pole top disconnect. During normal work hours.

$35.00
Reconnect fee disconnected for non-payment/ not requiring pole top disconnect. Not during normal work hours.

$75.00

Pole Top Disconnect Collection Charges

Collection charge per trip/ requiring pole top disconnect

$160.00
Reconnect fee disconnected for
non-payment/ requiring pole top disconnect. During normal work hours.

$160.00
Reconnect fee disconnected for
non-payment/ requiring pole top
disconnect. Not during normal work hours.

$225.00
Returned check charge

$25.00
Penalty 5% of the current net balance
 
 



Related Links:

Rate Schedules:


Schedule A:
Residential & Farm Service

Schedule RS:
Optional Residential & Farm Service


Schedule RE:
Optional Renewable Energy Rider


Net Billing Rate Schedule A and Distributed Generation Interconnection Standard


Schedule B:
Commercial & Small Power Service


Municipal Fire Signal Rider
to Schedule B



Schedule LP:
Large Power Service


Schedule OP:
Off Peak Service Rider


Schedule IPS - HLF:
High Load Factor Industrial Power Service

Schedule IPS - LLF:
Low Load Factor Industrial Power Service


Schedule EDR-4:
Economic Development Rate No. 4



Schedule REC:
Renewable Energy Credit Rider to LP, IPS and EDR-4


Schedule OSL:
Outdoor Security Lighting Service



Schedule PSL:
Public Service Lighting Service


Green Power